Our customer enquired about moving their extraction unit to the other side of the building as it was taking up too much space
Upon a site visit our design engineer determined it would be cheaper and easier to remove their current unit and replace it with a smaller and more efficient unit. This is because their current unit was taking in an abundance of product and using too much energy. We attended site to dismantle their old unit we’ve done this by striping the unit down in stages and removing them with a HIAB. Once the old unit was completely removed, we began to build up their new extraction unit and place it into position. Once the unit was in position, we then started to connect the ducting to their existing system.
On completion of the installation works, our commissioning engineer visited the customers site to carry out a LEV COSHH test to provide the customer with legal documentation for the new system.